What is "crashing"?


A) time until a capital asset completely wears out
B) reducing overall project completion time through the application of additional resources
C) very low capitalized value of a business's cash flows
D) time associated with the minimum of the equivalent annual costs
E) when a project's costs exceed the project's benefits by more than 10 times

F) D) and E)
G) A) and E)

Correct Answer

verifed

verified

As a rule, each project includes a feasibility study. With reference to the five-stage project management lifecycle, where does this feasibility study belong?

Correct Answer

verifed

verified

It's part of the initiation st...

View Answer

At what stage of a project's lifecycle can the project manager conclude that the project's goals have been met?


A) Initiation
B) Planning
C) Monitoring and control
D) Execution
E) Closure

F) A) and E)
G) B) and D)

Correct Answer

verifed

verified

The AON diagram shown represents a project. If the estimated times for each activity are as shown in the accompanying table, what is the estimated completion time for the project? The AON diagram shown represents a project. If the estimated times for each activity are as shown in the accompanying table, what is the estimated completion time for the project?     A) 16 days B) 20 days C) 26 days D) 30 days E) 32 days The AON diagram shown represents a project. If the estimated times for each activity are as shown in the accompanying table, what is the estimated completion time for the project?     A) 16 days B) 20 days C) 26 days D) 30 days E) 32 days


A) 16 days
B) 20 days
C) 26 days
D) 30 days
E) 32 days

F) A) and B)
G) A) and D)

Correct Answer

verifed

verified

Developing a new electronics product involves two activities that can be carried out independently: software development and hardware development. These activities would normally take 18 weeks and 20 weeks respectively, and the product development project is complete when both have been completed. If software development can be sped up at a cost of $1 million per week, and hardware development can be sped up at a cost of $2 million per week, what is the cost of reducing the project completion time to a)19 weeks and b)17 weeks?

Correct Answer

verifed

verified

a)$2 million (speed up hardwar...

View Answer

Who is responsible for the detailed project plan?


A) the project's sponsor
B) the government
C) the Canadian Engineering Association
D) the project's manager
E) the financial institution who finances the project

F) A) and E)
G) A) and D)

Correct Answer

verifed

verified

The AON diagram shown represents a project. Normal and crash times, and the associated costs, are shown for each activity in the accompanying table. If it is worth $5 000 a day to reduce the project duration, which activity or activities should be crashed? The AON diagram shown represents a project. Normal and crash times, and the associated costs, are shown for each activity in the accompanying table. If it is worth $5 000 a day to reduce the project duration, which activity or activities should be crashed?     A) There is no economical way to reduce completion time. B) Crash Activity 3 by 2 days. C) Crash Activity 7 by 2 days. D) Crash Activities 3 and 7 by one day each. E) Crash Activities 2 and 3 by one day each. The AON diagram shown represents a project. Normal and crash times, and the associated costs, are shown for each activity in the accompanying table. If it is worth $5 000 a day to reduce the project duration, which activity or activities should be crashed?     A) There is no economical way to reduce completion time. B) Crash Activity 3 by 2 days. C) Crash Activity 7 by 2 days. D) Crash Activities 3 and 7 by one day each. E) Crash Activities 2 and 3 by one day each.


A) There is no economical way to reduce completion time.
B) Crash Activity 3 by 2 days.
C) Crash Activity 7 by 2 days.
D) Crash Activities 3 and 7 by one day each.
E) Crash Activities 2 and 3 by one day each.

F) A) and B)
G) A) and C)

Correct Answer

verifed

verified

Which of the following project management tools is used to organize the work to be done in a project by decomposing the project into successively smaller units?


A) WBS
B) Gantt Chart
C) CPM networks
D) BCA
E) CN networks

F) A) and E)
G) A) and D)

Correct Answer

verifed

verified

A 5-year project requires $10 million in initial investment and will bring $0.5 million in net annual revenue under a 10% annual interest rate. If you were a project manager, would you proceed with project or would you terminate the project and at which stage?


A) Proceed with the project.
B) Terminate the project at initiation stage.
C) Terminate the project at planning stage.
D) Terminate the project at execution stage.
E) Terminate the project at monitoring and control stage.

F) A) and E)
G) B) and D)

Correct Answer

verifed

verified

A construction company has just started building a new house. It was estimated that the project will take 12 months. However, the owner of the land asked the company to complete it in 10 months. What should the construction company do to accommodate the owner's request?


A) To deliver the project on time, one or several project activities should be crashed.
B) To deliver the project on time, the company should hire extra workers.
C) To deliver the project on time, the construction company should work overtime.
D) To deliver the project on time, the construction company should look for a new technology.
E) To deliver the project on time, the construction company should change the project.

F) B) and E)
G) A) and B)

Correct Answer

verifed

verified